11th November 2006
Click on an image below for a larger version:
|
|
|
|
|
|
DG now has a full complement of elevons - here are the those on the port wing
|
The newly fitted port wing elevons
|
The newly fitted starboard wing elevons
|
The newly fitted starboard wing elevons
|
Gordon preparing the port TSN for the test fitting of a thrust reverse bucket
|
|
|
|
|
|
|
One of the thrust reverse bucket attachment points on the port TSN
|
Dad preparing the port TSN for the test fitting of a thrust reverse bucket
|
A thrust reverse bucket
|
The thrust reverse bucket is lifted into position
|
The bucket is bolted to its actuator jack
|
|
|
|
|
|
|
The movement of the bucket is checked using an electric drill to operate the screw jack
|
The underside of the port TSN showing the fitted lower bucket and its screw jack
|
The port TSN and its newly fitted lower thrust reverse bucket
|
Work is now complete on the new port side vortex generator
|
DG's nose is now complete with two vortex generators
|